Contractors for the U.S. Army Corps of Engineers Charleston District place material during the renourishment of Folly Beach on June 20, 2024 at Folly Beach, South Carolina. The Folly Beach Renourishment is a beneficial use project that serves three purposes – to renourish Folly Beach for coastal storm damage reduction, dredge the Folly River federal navigation channel, and place material on Bird Key to help reduce erosion on the critical bird habitat.

Contractors for the U.S. Army Corps of Engineers Charleston District place material during the renourishment of Folly Beach on June 20, 2024 at Folly Beach, South Carolina. The Folly Beach Renourishment is a beneficial use project that serves three purposes – to renourish Folly Beach for coastal storm damage reduction, dredge the Folly River federal navigation channel, and place material on Bird Key to help reduce erosion on the critical bird habitat.

SC Biz News Top Projects 2025 – Folly Beach Renourishment 2024

SCBiz Staff // September 30, 2025//

Listen to this article

The U.S. Army Corps of Engineers Charleston District completed a comprehensive coastal restoration project in October 2024, addressing Hurricane Ian damage across Folly Beach’s entire five-mile shoreline. The $25 million federally funded initiative placed 1.7 million cubic yards of sand over six months, transforming a complex engineering challenge into an innovative “beneficial use” project.

The renourishment strategically combined three separate objectives: restoring Folly Beach to its original design template, maintaining the Folly River Federal Navigation Channel through dredging, and renourishing Bird Key seabird sanctuary with 40,000 cubic yards of material. Rather than sourcing sand from offshore locations, engineers repurposed dredged material directly from the Folly River, significantly reducing costs and environmental impact.

Project execution required exceptional coordination during hurricane season, with contractors Gator Dredging and Marinex Dredging working simultaneously on different beach sections. Multiple storm delays, including Tropical Storm Debbie and Hurricane Helene, required equipment relocations and schedule adjustments while maintaining progress toward the October deadline.

The Charleston District developed an innovative interactive construction tracker featuring color-coded zones to communicate real-time beach access information to residents and tourists. Construction was strategically paused during Memorial Day, Independence Day and Labor Day weekends to support the local tourism economy.

Environmental stewardship remained paramount, with sea turtle monitors relocating nests and Bird Key restoration completed before nesting season. The project protects over $465 million in beachfront property and infrastructure while generating $238 in tourism revenue for every dollar invested in beach restoration.

Folly Beach Renourishment 2024

Folly Beach (entire beach)

PROJECT OWNERS: U.S. Army Corps of Engineers Charleston District; City of Folly Beach

PROJECT DEVELOPER: U.S. Army Corps of Engineers Charleston District

PROJECT CONTRACTORS: Gator Dredging; Marinex Dredging

PROJECT ARCHITECT: U.S. Army Corps of Engineers Charleston District

PROJECT ENGINEER: U.S. Army Corps of Engineers Charleston District